The construction site at salt. has sprung back into action after the Christmas break and the workers are pushing through on these hot summer days. The builders, iLine, are on track with the building programme. There are a limited number of homes remaining. To find out more, contact Grant White 021 981 007.

 

Block C has bock work partition walls up to the underside of Level 2 installed. The supporting structural steel is in place ready to start receiving the pre-cast concrete floor beams in readiness for a concrete pour to Level 2 in the next few weeks.

 

Block A has all block work to underside of Level 1 completed with the intricate structural floor beams well underway. The first pre-cast concrete balcony has been placed, with the balance of the balconies being delivered over the next few weeks to enable the Level 1 slab pour in early March. Off-site fabrication of structural steel and pre-cast is underway.

 

Block G is the most advanced of the townhouses, with block work up to underside of Level 1 almost complete, with pre-cast stairs and floor being delivered shortly.

 

Block E (left hand side of image) foundations and underfloor services have started with an expected floor pour in 3 weeks while Block D (right hand side of image) has all foundations completed, underfloor services and Ground Floor slab being poured in late February. Block F & H and the childcare centre are also due to commence over the next few weeks.