View from Block C Level 2

Construction at Salt. has been progressing well over the previous months.

Block C roof commencing

 

In Block C the block work is now complete and all floors have been poured. The internal fit out has commenced on ground floor and level one and the windows are starting to go in on these levels. Services have also commenced to the apartments as well as the off-site procurement of aluminium windows, doors, lifts and precast panels. The next stage will be the roof structure, of which the structural steel has recently started.

Block A east facing apartments

In Block A the internal framing has commenced on the ground floor and level 2 flooring has been poured with block work and structural steel soon to commence.

Block A apartments and Block G townhouses

Block D townhouses

Block G townhouses

The townhouses are also progressing well, with all level 1 flooring poured except Blocks E, F and H.  Blocks G and D roofs will be going on over the next few months, which will be followed by Blocks E, F and H.

Childcare centre floor slab

The childcare slab has been poured and the roof will be going on over the next few weeks.

There is still time to be part of this community. There are a limited number of homes available. To find out more, please get in contact with Grant White.